The 1,468-place prison at Grendon Underwood should open by the end of 2031. Construction traffic is capped at 250 vehicles a day at the peak.
The new Category C prison at Grendon Underwood is expected to open by the end of 2031. That date is in a Ministry of Justice report written for Buckinghamshire councillors, who will question the project team on Tuesday 17 November.
The prison will hold up to 1,468 men. It is being built next to HMP Grendon and HMP Springhill, about ten miles north-west of Aylesbury. The ministry says that, subject to a future ministerial decision, it expects the prison to be privately run.
How it got here
Buckinghamshire Council refused the plans, and the government overturned that refusal. The council’s own report to the committee sets out the steps.
| Date | What happened |
|---|---|
| 29 March 2022 | Council refuses outline planning application 21/02851/AOP |
| 24 January 2023 | Eight-day public inquiry opens |
| 30 January 2024 | Secretary of State allows the appeal |
| 31 October 2025 | Appearance and landscaping approved (25/02292/ADP) |
| 7 August 2026 | Construction traffic plan approved (PL/26/03123/CONDA) |
| End of 2031 | Expected opening |
The council’s refusal reasons covered the location, heritage, biodiversity, landscape, protected species and the loss of playing fields. The Secretary of State accepted there would be harm to the landscape and to the settings of Grendon Hall and Lawn House. The Secretary of State decided the need for prison places and the economic benefits outweighed it.
The council’s report is blunt about what that means now. It “cannot revisit the principle of the prison” through the conditions or the traffic plan.
What is being built
According to the council’s report, the permission covers:
- six houseblocks for up to 1,468 prisoners
- up to 67,000 square metres of buildings inside a secure perimeter
- 453 operational parking spaces
- internal roads, perimeter fencing and supporting buildings
The ministry’s report says the prison will be all-electric and use around 70% less energy than older prisons. It is aiming for a 14% biodiversity net gain, above the 10% legal minimum. Laing O’Rourke is the main contractor.
It will be a resettlement prison, preparing men for release through education, workshops and training. The ministry gives the national context: it is one of the new prisons meant to add 14,000 places by 2031.
The lorries, and where they will go
Construction is the part residents will feel. The council’s report says the main building programme is scheduled to run for 306 weeks, which is almost six years. It describes this as “a substantial multi-year construction programme rather than a short-term construction impact”.
Three construction entrances are in use or planned:
- Lawn Hill, the main entrance for lorries during the enabling works and for site workers throughout
- Grendon Road, which becomes the main lorry entrance once the main building works start
- Springhill Road, the existing prison entrance, used only until the main works begin
Lorry routes run to the A41 and the A421. Abnormal loads need special arrangements because of bridge height limits on the A41.
The council’s highways assessment records a cap of 250 vehicles a day at the peak. It notes that a lorry’s arrival and its departure count as separate movements.
For now the work is at the early enabling stage. During this stage Lawn Hill is limited to 50 lorry arrivals and 50 departures a day. The council says monitoring so far shows lorries are keeping to the approved routes.
The approved traffic plan also includes:
- booked delivery slots and a cap on vehicles each hour
- a 30mph maximum for construction vehicles approaching and leaving the Lawn Hill entrance
- passing places and possible widening on Lawn Hill, subject to highway approval
- wheel washing, road sweeping and surveys of road and verge condition
- monthly traffic reports that the council can review
Every lorry working on the prison carries an identifier in its windscreen. Laing O’Rourke has a traffic ambassador at Lawn Hill and is recruiting a second for Grendon Road and Springhill Road. Drivers found on the wrong route are turned away, the council’s report says.
HS2 on the same roads
The prison is being built in the same corner of the county as HS2. The council says it is “concerned by the cumulative impact of major infrastructure works”.
Since November 2025 the HS2 contractor EKFB and the ministry have met every month. They share closures, lorry routes and lorry numbers, and the ministry attends HS2’s monthly traffic liaison group.
Jobs
The ministry’s report sets these targets for the main contractor during the main works:
- 25% of on-site workers from within 50 miles
- 40% of off-site workers from within 50 miles
- 40% of project spending within 50 miles
- 50 apprentices or trainees
It points to HMP Millsike in Yorkshire, which opened in 2025, where 46% of the on-site workforce was local.
What it means for you
If you live in Grendon Underwood, Edgcott or along Lawn Hill, this is close to six years of construction traffic. The council’s report lists the worries people have raised with it, including lorries on Lawn Hill, the safety of walkers, cyclists and horse riders, noise, dust, mud and damage to verges.
The ministry and Laing O’Rourke are responsible for keeping to the traffic plan. The council says it will check the monitoring data and can act where the evidence shows the plan is not being followed. Any material change to the plan needs the council’s approval first.
General questions about the project go to the ministry at psdenquiries@justice.gov.uk.
The Growth, Infrastructure and Housing Select Committee takes the item at about 11am on Tuesday 17 November at The Oculus, Gatehouse Road. The meeting page has the agenda and a link to the webcast.