Barratt David Wilson's review says the 1,100-home Aylesbury Woodlands scheme at Aston Clinton is £139.34m in deficit. Comments close on 14 December.
The developer of Aylesbury Woodlands has asked the council to sign off the first steps towards building homes there. Its viability review says the scheme is £139.34m in deficit. Comments close on 14 December.
Buckinghamshire Council validated the application on Thursday 19 November, in the week starting 16 November. It is on the council’s weekly list of new applications.
Aylesbury Woodlands: viability review, design code and phasing plans
Aylesbury Woodlands is the land between the A41 Aston Clinton Road and College Road North, on the Aston Clinton side of Aylesbury. Its outline planning permission, 16/01040/AOP, allows for:
- up to 1,100 homes and 60 extra care homes;
- up to 102,800 square metres of offices, industry and warehouses;
- a local centre of up to 4,000 square metres;
- a hotel and conference centre of up to 5,700 square metres;
- up to 16 hectares for a sports village and pitches;
- up to 2 hectares for a primary school;
- a link road between the Eastern Link Road and the A41.
The new application, PL/26/09461/MDLA, is from BDW North Thames, part of Barratt David Wilson Homes. It asks the council to approve four parts of the scheme’s section 106 agreement:
- the first and second revised financial appraisals, which test what the scheme can afford;
- a landscape phasing strategy;
- a plan for building and managing the site in phases, numbered 0 to 3;
- a six-part design code, also sent in under condition 10 of the permission.
The agreement sets a minimum of 20 per cent affordable homes. Of those, 60 per cent are for affordable rent and 40 per cent for shared ownership. It also makes the developer rerun the sums four times as building goes on. If a later review shows a surplus, it goes on more affordable homes or a payment towards education, up to a cap.
The appraisals are by Turner Morum, for the developer, and both are dated 3 November 2026. They say:
- the whole scheme is in deficit by £139.34m;
- site-wide infrastructure costs come to about £116.22m;
- section 106 contributions total £16.6m;
- the sums assume a grant of about £24.8m that will not need to be paid back.
The report puts the deficit down mainly to the method the agreement requires. Because it shows a deficit, it says no extra affordable homes or contributions are due. The author adds: “I cannot see any circumstances where a surplus could be illustrated.”
Under the agreement, the phase called 1B cannot start until the first appraisal is approved by the council’s consultants or settled by an independent expert. The first detailed application for a housing phase cannot go in until the second appraisal is approved.
The appraisals, the design code and the phase plans are all in the application’s documents. The council’s consultation runs to Monday 14 December. The council aims to decide by Thursday 14 January 2027.
Also applied for this week
- Creslow Manor, Creslow: notice of plans to demolish two former farm buildings, PL/26/09464/DM. The council has until 15 December to respond.
- Lower Way, Padbury: a 13-metre wooden telecoms pole opposite Pointers View, PL/26/09650/TELN. The council acknowledged the notice on 23 November.
How to comment
Comments go through Buckinghamshire Council’s planning portal, on each application’s own page, before the date shown there.